Final Turbine Successfully Installed for EOWDC

Monday 28 May 2018

The final turbine for the European Offshore Wind Deployment Centre (EOWDC) has been successfully installed with the project recording what is believed to be the world’s fastest installation of a gigantic, game-changing suction bucket jacket foundation.

Saturday’s (26th May, 2018) turbine installation comes just nine weeks after the first foundation for the 11-turbine EOWDC scheme off Aberdeen Bay was deployed in the North Sea.

The ground-breaking 93.2MW EOWDC, which is scheduled to generate first power in the summer, will produce the equivalent of more than 70% of Aberdeen’s domestic electricity demand and annually displace 134,128 tonnes of CO2.

It features nine 8.4MW turbines along with two 8.8MW models which both represent an industry first in that they are the first of this power capability to be deployed commercially in the offshore wind industry. As a result, all turbines will enable the EOWDC to generate more clean energy.