Petroleum Safety Authority Norway Have Granted Statoil Consent to use a Replacement Pipeline on the Heidrun Field
Friday 11 May 2018
Petroleum Safety Authority Norway have granted Statoil consent to use a replacement pipeline between Heidrun and subsea structure E on the Heidrun field.
The replacement of the Heidrun P-E pipeline is part of a project to develop and extend the life of Heidrun Nordflanken by 20 years.
The new pipeline will be installed in May/June 2018 and anticipated start-up is between July and September 2018.
The Heidrun field
Heidrun is on Haltenbanken in the Norwegian Sea, 30 kilometres north-east of Ã…sgard. The PDO for Heidrun Nordflanken was approved in 2000. The northern part of the field has been developed using subsea facilities.