EDS HV Group Successfully Completes Scope of Work at Rampion
Tuesday 6 March 2018
High voltage engineering specialist, EDS HV Group (EDS), now part of the UK’s leading marine services company – James Fisher and Sons plc, has successfully completed its scope of work for cable termination and testing works at the Rampion Offshore Wind Farm. EDS worked as a tier 1 contractor on this project and completed their scope of work on target and as per the programme.
The Rampion development, located off the Sussex coast in the UK, features 116 turbines each 3.45MW in capacity, giving the project a total generating capacity of 400MW. EDS successfully completed the termination and testing of 116 assets as well as completing jointing activities on the offshore substation and on the two 150kV export cables. EDS also assisted with onshore commissioning activities.