DEA: Dvalin Template Delivered on Time by Aker Solutions
Friday 26 January 2018
The Dvalin project reach a major hardware milestone as Aker Solutions deliver template on time.
After 10 months of production at the Aker Solutions yard in Egersund, the template is handed over to DEA according to both time and budget.
The Integrated Template Structure (ITS) will be stored in Egersund until load out and installation on the Dvalin field by TechnipFMC, which is currently planned to take place in April 2018.
Aker Solutions in Egersund will continue the assembly work on the manifold module, which is on schedule for delivery in Q1 2019.