Hurricane Energy plc Operational Update and Analyst Visit
Tuesday 12 December 2017
Hurricane Energy plc, the
The Aoka Mizu FPSO ("Aoka Mizu"), the facility for the Lancaster EPS, arrived in
An analyst site visit to these operations will take place on 12-13 December 2017, prior to which, the Company provides the following update:
· Internal turret removed from Aoka Mizu for upgrade
· First planned dry-docking completed on schedule, during which a number of works were undertaken, including: removal of a thruster for overhaul, outer hull surveys, replacement of a number of sea valves, and installation of new bilge keels
· Initial tank inspections and cleaning has taken place
· Buoy structure is taking shape, with major sections including the top cone preassembled and shell plating being attached to the cone module
· Buoy locking ring has arrived from fabricator and is being installed
· All critical components for the mooring are now undergoing fabrication and the first of the 12 chains has been completed