Audit of Waves on Deck at Veslefrikk B
Monday 23 October 2017
On 31 August 2017, we carried out an audit of Statoil Petroleum AS (Statoil) and waves on deck at Veslefrikk B.
20.10.2017 Print Tip someone Register for news
Objective
The objective of the audit was to understand the status of Statoil's own follow-up for securing semi-submersible production facilities and tension leg platforms against waves on deck. We also wanted to gain an insight into Statoil's routines and criteria for when measures are necessary to secure the facilities in given sea states. This task was focused in particular on Veslefrikk B, while the other facilities are covered by a planned meeting in October.
Result
No non-conformities were identified.
An improvement point was identified concerning the decision support from analyses.
Statoil has been given a deadline of 26 October 2017 to report on how the improvement points will be addressed.