Woodside Operational Update

Thursday 19 January 2017

WHEATSTONE:

First LNG from Train 1 is expected in mid-2017 and from Train 2 six to eight months later.1

All Train 1 and Train 2 modules are set on their foundations. Installation of

piping, electrical and instrumentation continues as planned.

The storage and loading system is ready for commissioning and cool-down,

with the LNG storage tanks and export loading jetty now complete.

Woodside’s forecast 2017 capital expenditure for Wheatstone and Julimar

Projects is approximately US$370 million, consistent with previous guidance.

GREATER WESTERN FLANK:

The final GWF-1 project wells at Tidepole delivered first gas in Q4 2016.

The project was completed ahead of schedule and under budget.

PERSEPHONE:

The project remains on budget and schedule for start-up in Q3 2017.

At the end of the quarter, progress was 89.8% complete versus 84.2% planned.

The project completed the reservoir drilling and completions campaign and commenced subsea installation.

GREATER ENFIELD:

The project remains on budget and schedule for first oil in mid-2019.

At the end of the quarter, progress was 8.6% complete versus 6.4% planned.

The manufacture of subsea equipment has commenced.