DolWin3 Clear: SeaTerra Completes Investigation of 278 Objects and Removal of Eight Ordnance Targets from the DolWin3 Cable Route

Wednesday 24 August 2016

Commissioned by the transmission system operator TenneT, SeaTerra GmbH examined and cleared in recent weeks and months numerous metal objects from the future DolWin3 cable route between Emden and the seaward converter platform DolWin alpha. The DolWin3 project establishes a 900 megawatt (MW) direct current (DC) grid connection for offshore wind farms in the south‐western part of the German North Sea (offshore wind farms Merkur Offshore and Borkum Riffgrund 2).